How to choose the gravel production line equipment



1, how to build sand stones factory, stones factory, quarries, gravel plant, sand plant, mines?

The first step is to investigate the market, to see whether the market prospects in this business, how to profit? Marketability How? Do not fight blind battle.

The second step selected mines or river, for the relevant mining procedures, this is a must, otherwise even hastily produced, will be a lot of trouble.

The third step is to examine the device, select a relatively strong strength of all aspects of the manufacturers, a set of excellent quality sand and gravel production line

equipment.

The fourth step, when buying the sieve classification stone screening machineequipment, these devices does not work, is just one part of the crushing and screening machinery,

engineering machinery need to be addressed, such as loaders, excavators, transport vehicles, issues, and blasting mining equipment problem.

The fifth step, installation and commissioning of all equipment in place after commissioning, recruit workers, fixed mining system, a management, contact customers, production

and sales, in fact, a considerable part of the actual operation is the first customer to reinvest factories production, sales is the first one .

2, commonly used gravel production line, dewatering screen production line, aggregates production equipment needs what machinery?

Crushing and screening, aggregates production lines, including coarse jaw crusher, fine jaw crusher, impact crusher, cone crusher, hammer crusher, roll crusher, vertical shaft

impact crusher (sand making machine), vibrating feeder, vibrating screen, sand washing machine, in order to

And the type of conveyors and other equipment. Press the installation is divided into fixed, semi-mobile and mobile three, the processing capacity of 10 ~ 500t / h, product size

and grade distribution according to user needs, usually 0 ~ 40mm.